Wednesday, 17 October 2012

SLAKED LIME MID (149) AND FRIENDS

PAM AND DAVE WENT OVER TO ASHBOURNE THIS MORNING TO COLLECT THE PAINT ORDER FOR US!


PETE HAS FINISHED THE TILING THE PORCH ROOF!- ITS A TRIUMPH

WE CONTINUED WITH THE MASONRY PAINTING TODAY, TAKING ADVANTAGE OF THE DRY WEATHER.


HERE IS THE FRONT OF THE HOUSE WITH THE FIRST COAT OF THE FINISHED COLOUR- AND I COULD NOT BE HAPPIER IT IS JUST WHAT I WANTED- IT WAS WORTH ALL THE EFFORT IN CHOOSING THE RIGHT SHADE

 
 
MORE OF THE CLADDING IS GOING ON AROUND THE BACK OF THE HOUSE.


 
SLOWLY BUT SURLEY ITS ALL GOING IN THE RIGHT DIRECTION, PETE HAS ODRDERED EVERYTHING FOR GLAZING THE WINDOWS THE PAINTED CLADDING IS GETTING A SECOND COAT OF STAIN AS IT GOES ON THE ARCHES ARE NEARY DRY ENOUGH FOR A FIRST COAT OF PAINT AND WE ARE LOOKING AT PAINT OPTIONS FOR THE CILLS, INSIDE THE REST OF THE RADIATORS HAVE BEEN DELIVERED AND THE WARMCELL INSULATION HAS BEEN BOOKED FOR NOVEMBER.